MGMT 335 HW#5 Please solve the following problem: As part of a

MGMT 335 HW#5

Please solve the following problem:

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:

Task

Duration (minutes)

Immediate Predecessor

A

0.6

B

0.5

A

C

0.3

B

D

0.4

E

1.8

D

F

0.8

C

G

1.2

E, F

Do each of the following:

Draw the precedence diagram.

Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.

Determine the minimum number of stations needed.

Use a table to assign tasks to workstations on the basis of most following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

Compute the percentage of idle time for the assignment in part d.