Term Project MGT4495E1 Project Management Foundations Project Documentation for Backyard Landscaping Project

Term Project

MGT4495E1 Project Management Foundations

Project Documentation for Backyard Landscaping Project

Fist name Last Name

Date

Introduction – High-level narrative of what the project is about, Who the project manager and project sponsor is, and when the project is to start and end. You are the project manager.

Project Charter

Project background

Critical success factors

Required resources

Constraints

Approvals

Communication Plan

Introduction- Use the definition from the PMBOK of a Communication Plan

Describe what the table below is telling you.

Stakeholder

Name

Message/Info Need

Delivery Vehicle

Frequency

Project Sponsor

Project Manager

Project Team Members

Quality Team Members

Procurement Team Members

Other Stakeholders

Project Quality Plan

Introduction- Use the definition from the PMBOK of a Quality Plan

Describe what the table below is telling you.

Name/Title

Agency/Department

Project Role

Responsibility

Phone

Email

Quality planning – Definition from PMBOK and specific to this project

Quality assurance activities – Definition from PMBOK and specific to this project

Quality Control activities – Definition from PMBOK and specific to this project

Project Risk Plan

Introduction- Use the definition from the PMBOK of a Risk Plan

Describe what the table below is telling you.

Risk

Risk Probability

Impact Description

Level of Impact

Date of Impact

Priority level

Risk Management Plan (Mitigation Plan)

Project Schedule

Introduction- Use the definition from the PMBOK of a Project Schedule or WBS

Describe what the table below is telling you.

Account Code

Task

Duration (Days/Hour)

Labor

(Hours)

Resource name

1.0

Design home landscape

5 Days

80

Homeowner

2.0

Put in lawn

2.1

Purchase lawn materials

2 Days

64

Homeowner

2.2

Install Sprinkler System

2.2.1

Identify sprinkler locations

1 Day

Fixed Fee

Contractor

2.2.2

Dig Ditches

2 Days

Fixed Fee

Contractor

2.2.3

Install pipe and hardware

3 Days

Fixed Fee

Contractor

2.2.4

Cover sprinkler system

1 Days

Fixed Fee

Contractor

2.3

Plant grass

368

2.3.1

Remove debris

4 Days

256

Teens

2.3.2

Prepare soil

6 Days

96

Teens

2.3.3

Plant lawn seeds

1 Day

16

Teens

2.4

Plant Shrubs

8 Days

96

Teens

3.0

Build Fence

344

3.1

Acquire fence materials

2 Days

16

Homeowner

3.2

Install fence

328

3.2.1

Mark fence line

1 Day

32

Homeowner

3.2.2

Install posts

7 Days

80

Teens

3.2.3

Install fencing and gates

8 Days

144

Teens

3.2.4

Paint/stain fence and gates

5 Days

72

Teens

4.0

5.0

Conclusion

Purpose of the project – summarize what the project is about (re-state the Introduction)

Stakeholders – Who are the stakeholders?

Outcome – State that project was a success and how you know. State any risks that turned into issues you had to mitigate and how you were successful.

Lessons Learned – What went wrong and what you would do differently.

1