PROJECT CHARTER
Project Title: Construction of an outdoor swimming pool in a resort
Project Sponsor: Carl (Resort owner)
Date Prepared: 11/6/2021
Project Manager: Raaga
Project Customer: John
Project Purpose:
To construct an outdoor swimming pool in a resort to provide customers with comfort and luxury as well as to increase the income of the resort.
High-Level Project Description:
Constructing an outdoor swimming pool in a resort adds extra income to the resort as well as gives satisfaction and comfort to the customers who check in.
Project Boundaries:
Pool side dining is not available.
Free membership for customers is not a part.
Key Deliverables:
Constructing an outdoor swimming pool in a resort
High-Level Requirements:
People, equipment like machinery and tools. materials like cement, bricks tiles are required.
Overall Project Risk
The project risk could be the current customers who already checked in the resort might feel the disturbance due to this construction work and because of this the income during the construction phase might drop down.
Project Objectives
Success Criteria
Scope:
Constructing an outdoor swimming pool in the resort.
The pool provides facilities to the customers and also increases the income of the resort. It also attracts new customers for functions and parties to take place.
Time:
The swimming pool will probably be finished within four months of timeline
The expected deadline would meet without any delays.
Cost:
The cost of the project would be around $17,000
The estimated cost would not exceed the budget.
Other:
Click here to enter text.
Click here to enter text.
Summary Milestones
Due Date
Excavation work
11/22/2021
Raw materials delivery
12/23/2021
Construction of pool
1/15/2022
Placing tiles in the pool
1/30/2022
Adding extra attachments
2/10/2022
Preapproved Financial Resources:
The estimated budget for the project is $17,000, but the partial amount of $8000 is required to start the work.
Stakeholder(s)
Role
John, Jim
Customers
Mary, Katy
Resort employees
Mike, Sam
Residents nearby resort
Project Exit Criteria:
Successful completion of the outdoor swimming pool with all the attachments.
Project Manager Authority Level:
Staffing Decisions:
The staff is selected based on their skills and experience levels.
The project manager would monitor the performance.
Budget Management and Variance:
The project manager would be responsible for the budget allocation and if the amount gets exhausted then sponsor would release the amount.
Technical Decisions:
A technical expert is hired to monitor and update the status of the project.
Conflict Resolution:
The project manager would be solving the conflicts incase if they occur and if still unresolved then a meeting between project sponsor and members is been assigned.
Sponsor Authority:
Taking the important decisions during conflicts and
Managing the funds when exhausted.
Approvals:
Click here to enter text.
Click here to enter text.
Project Manager Signature Sponsor or Originator Signature
Raaga
Carl
Project Manager Name Sponsor or Originator Name
Raaga
Carl
Date 11/6/2021
Date 11/6/2021
ASSUMPTION LOG
Project Title: Construction of an outdoor swimming pool in a resort
Date Prepared: 11/6/2021
WBS Task ID
Category
Assumption
“We are unsure of ________, so we assume that…”
Responsible Party “Who will complete the task/action?”
Due Date “When must the task be completed by?”
Actions (Task in WBS)
Status (Open/Closed)
Comments (Keep track of steps taken)
1
Pre construction phase
Assuming that the project would get completed within estimated time
Raaga
3/6/2022
The project manager is responsible for the allocated time
closed
The project manager would maintain the details of deadlines finished.
2
Procurement phase
Assuming that the raw materials would be delivered on time
Raaga
12/23/2021
The project manager is responsible for the delivery of raw materials on time
closed
The project manager would keep in contact with the contractor.
3
Construction phase
Health of the workers is been taken care by doctors on site
Rose
2/10/2022
The health care doctor is responsible for the health of workers
closed
Doctor maintains the record of the health of each employee.
4
Construction phase
Scope of the project is maintained same by the project sponsor
Carl
2/2/2022
The scope is maintained and done perfectly by the project sponsor
closed
The project sponsor keeps a track of the finished deadlines.
SCOPE MANAGEMENT PLAN
Project Title:Construction of an outdoor swimming pool
Date: 11/12/2021
Work Breakdown (WBS) Structure
WBS means the work break down structure. In this project of Construction of an outdoor swimming pool there are so many deliverables. They are as follows:
Construction of an outdoor swimming pool, 1.1 Plan, 1.1.1 Blue print, 1.1.2 Permission and approvals, 1.1.3 Funds, 1.2 Resources, 1.2.1 Raw materials, 1.2.1.1 Bricks, 1.2.1.2 Cement, 1.2.1.3 Sand, 1.2.1.4 Tiles, 1.2.2 Equipment, 1.2.2.1 Cranes, 1.2.2.2 Bulldozer, 1.2.2.3 Trucks, 1.2.3 Workers, 1.2.3.1 Night shift workers, 1.2.3.2 Day shift workers, 1.2.4 Extra attachments, 1.2.4.1 Hardware attachments, 1.2.4.1.1 Ladders, 1.2.4.1.2 Lights, 1.2.4.1.3 Heat pumps, 1.2.4.1.4 Doors, 1.2.4.1.5 Windows, 1.2.4.1.6 Hammocks, 1.2.4.1.7 Showers, 1.2.4.2 Life savers, 1.2.4.2.1 Life jackets, 1.2.4.2.2 Tubes,1.2.4.2.3 Float boards, 1.2.4.3 Basic needs, 1.2.4.3.1 Swim suits, 1.2.4.3.2 Caps, 1.2.4.3.3 Goggles.
WBS Dictionary
The WBS dictionary contains the WBS level, WBS code, WBS name and the WBS description where the WBS dictionary explains about the deliverables and tasks in detail.
Scope Baseline Maintenance
The scope baseline is maintained and monitored frequently. Incase if there are any changes to the scope of the project like needed extra tiles for the pool then the change request will happen and project manager will deal with it.
Deliverable Acceptance
The construction of an outdoor swimming pool is the main deliverable and it is accepted only if it has a proper base with tiles, heat pumps that regulate the temperature of the water in the pool, lights and ladders must be installed and along with extra attachments like life jackets, tubes and float boards.
Scope and Requirements Integration
The requirements of the project are being collected by the project manager from the project sponsor, customers and the stakeholders by conducting an interview with them face to face or virtually. Then they are placed in the scope statement and deliverables are made once the requirements are clearly stated.
PROJECT SCOPE STATEMENT
Project Title:Construction of an outdoor swimming pool
Date Prepared: 11/12/2021
Project Scope Description:
Constructing an outdoor swimming pool in the resort in order to provide customers with more facilities and also attract new customers and increase the income of the resort.
Project Deliverables:
Placing the tiles inside the pool.
Fixing lights inside the pool.
Installing the heat pumps.
Fixing the ladders inside the pool.
Building two changing rooms and a shower chamber next to the pool.
Adding the swimming tubes, float boards and life jackets post construction of the pool.
Placing the hammocks next to the pool.
Building a stall that sells swimsuits, goggles, caps and some refreshments.
Product Acceptance Criteria:
Quality of raw materials like bricks, cement, tiles should be maintained properly.
The lights and wiring should be shock proof and water proof.
Heat pumps with larger power capacity.
Extra attachments like ladders, shower chambers and hammocks should pass the quality check before installation.
Life jackets are tested in prior to usage.
Project Exclusions:
The pool side dining is not available.
Free membership for the customers is not a part.
Project Constraints
Quality of raw materials should be maintained.
Successful delivery of goods without any damage.
Permission to start the construction of the pool.
Sufficient workers to finish the project.
Reaching the milestones successfully to finish the project.
Project Assumptions
Assuming that the raw materials are in perfect condition without any damage.
Installation of the ladders, lights and heat pumps are done correctly by the trained people.
Health of the workers are taken care by the doctor onsite.
project sponsor does not change the scope of the project.
FORMAL ACCEPTANCE FORM
Project Title: Construction of an outdoor swimming pool
Date Prepared: 11/15/2021
ID
Requirement
Acceptance Criteria
Validation Method
Status
Comments
Sign-off
1.2.1.4
Placing the tiles
Accepted when tiles are in good condition without any damage and are of good quality.
Manual checking by person is done after the delivery.
open
Click here to enter text.
Click here to enter text.
1.2.4.1.1
Fixing ladders
Should be strong and of good quality
Tested manually by person before purchasing.
open
Click here to enter text.
Click here to enter text.
1.2.4.1.2
Fixing the lights
Lights should be water proof and shock proof
Checked before installing them in the pool by conducting a demo manually
open
Click here to enter text.
Click here to enter text.
1.2.4.1.3
Installing the heat pumps
Should have larger power capacity
Tested before purchasing the product.
open
Click here to enter text.
Click here to enter text.
1.2.4.2.1
Life jackets
Quality should be good and reliable
Prior testing is done manually
open
Click here to enter text.
Click here to enter text.
1.2.4.2.2
Tubes
Quality of the tube should be good
Testing is done manually
open
Click here to enter text.
Click here to enter text.
1.2.4.2.3
Float boards
Should withstand heavy weight
Trials are done before purchasing the product
open
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
GROUP ACTIVITY LOG
Project Title: Construction of an outdoor swimming pool
Date Prepared: 11/16/2021
S.NO
Team members
Tasks
Time spent
Tools/Techniques used
1.
Raaga Ratakonda
Project charter, WBS, Project scope statement
15hrs
PMBOK, Book of forms, zoom, word, MS projects, Research documents, conduct group meetings.
2.
Sai Saketh Vemuganti
Formal acceptance form, Assumption log
12hrs
PMBOK, Book of forms, zoom, research documents.
3.
Bhargav kumar Raval Udaybhai
Scope management plan, WBS dictionary
11hrs
PMBOK, Book of forms, MS projects.
2